Kenya launches Chinese-built fast train

China Daily Africa | Updated: 2017-05-28 08:23

The eagerly awaited inauguration of Kenya's modern railway infrastructure is set for May 31. The $3.8 billion Standard Gauge Railway, developed by China Road and Bridge Corp, has been completed six months ahead of schedule. It is expected to lower the cost of doing business in East Africa as it enables the transportation of freight from the port of Mombasa to Nairobi, with later connections to neighboring Uganda and Rwanda.

Here is a chronology of the milestones of the 472 km Nairobi-Mombasa route:

Phase I

Aug 12, 2009: CRBC signed MoU with Kenya Railways Corp.

2012: Submitted the preliminary design. Civil works contract and supply and installation of facilities, locomotives and rolling stock contracts signed.

Aug 19, 2013: President Xi Jinping and President Uhuru Kenyatta jointly witnessed the signing of the MoU on financing the Mombasa-Nairobi SGR Project.

May 11, 2014: Premier Li Keqiang witnessed the signing of the financing agreement with heads of state from East African countries.

Phase II

Dec 12, 2014: Project construction officially commenced.

Jan 23, 2015: Kenyatta visited the standard gauge railway observation segment of Section 3, and track-laying base of Section 6.

May 26, 2015 : Kenyatta visited the construction site of the Tsavo River Super Bridge.

Sept 19, 2015: Kenyatta and China Communications Construction Co President Chen Fenjian jointly attended the ground-breaking ceremony of the Nairobi Terminus.

Oct 30, 2015: Track-laying work commenced and operation planning and locomotive purchase started.

March 26, 2016: Zhang Dejiang, chairman of the Standing Committee of National People's Congress, went to Mombasa to see the Mombasa Terminus of Mombasa-Nairobi SGR Project.

Aug 10, 2016: Kenyatta met with Chinese Foreign Minister Wang Yi in Nairobi, showing willingness to actively promote the early completion and operation of the project and jointly build the East Africa Railway Network.

Late December 2016: The first locomotives were shipped.

Phase III

Beginning of 2017: Integration test and commission started.

June 1, 2017: Trial operation of SGR Project.

January 2018: Officially opened to traffic.

 Kenya launches Chinese-built fast train

Thousands of young men and women have had the chance to be part of the team behind the success of the Standard Gauge Railway Project.

?

?

 

Polar icebreaker Snow Dragon arrives in Antarctic
Xi's vision on shared future for humanity
Air Force units explore new airspace
Premier Li urges information integration to serve the public
Dialogue links global political parties
Editor's picks
Beijing limits signs attached to top of buildings across city
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
太白县| 宜宾县| 肃宁县| 富锦市| 北安市| 张掖市| 恩施市| 青岛市| 濮阳市| 成安县| 余干县| 巴林右旗| 甘孜县| 资阳市| 郑州市| 武穴市| 城固县| 上饶市| 娄烦县| 兴安县| 百色市| 凯里市| 永福县| 满洲里市| 静乐县| 体育| 延安市| 淮北市| 夏津县| 肥城市| 五常市| 西乌珠穆沁旗| 海原县| 德惠市| 蚌埠市| 常德市| 奉节县| 石首市| 嘉鱼县| 民丰县| 根河市|